Sunday 6 May 2012
Gov Uduaghan explains N7.4bn airport expenditure
The Governor of Delta State, Emmanuel Uduaghan, has said that the N7.4
billion budgeted for the earth movement at the Asaba International
Airport was to enhance pilots’ visibility and for the airport to
accommodate large body aircraft. He explained that his administration
was abiding by the conditions given by the aviation regulatory body, the
Nigeria Civil Aviation Authority (NCAA). Speaking to selected Aviation
Correspondents in Asaba at the weekend, the Governor said that work had
started on the project long before the planned visit of the President
for the South South Economic Summit, remarking that the airport was
built with 3.4 kilometer runway with 50 metres width, which qualifies it
to accommodate a Boeing 747 aircraft and its equivalent. He however
added that there are conditions that must be met before such aircraft
could be allowed to land by the regulatory body. Such conditions,
according to him, include having a strip of 120 meters on either side of
the runway, and that the ends of the runway must be at the same ground
level with the runway. “ So inevitably the hill at the end of the runway
must be cut down and the earth moved to the sloppy sides of the runway
so that there is equal ground level distance of 300 meters on either
side of the runway. “So the N7.4 billion was not budgeted just for
cutting of the hill but for complete earth work to ensure that the
runway is at the level of its surrounding so that the airport meets
international standard for easy visibility of the pilot, the landing and
take-off of large body aircraft and for safety at the runway and the
whole airside of the airport”, he said Uduaghan added, “The contract for
the leveling of the hills was not awarded because of the recently
concluded South South Summit we hosted in Asaba; it is purely driven by
the technical and safety consideration of the NCAA. The contract has
since 2011 been awarded, as the Chief Executive of the state, I directed
the contractor to get the job done in good time because we are in a
hurry to get the airport up and running, that is our goal and this is
driven by the pressure I am under from our sister states in the South
East, Anambra, Abia, Enugu to get the airport running.” The Governor
also explained that the contractor had done about 10 percent of the job
after about 10 months, calculating that with that pace job would be
completed in the next two years, which was not what government, which
was already under pressure to kick off the cargo part of the air
operation, so government had to bring in two more contractors at the
same budget of N7.4 billion to finish the job in time. On the amount of
money budgeted for the project, the Governor said, “I think the figure
that is being bandied about is the totality of so many things, the
unfortunate thing is that the time the figures were sent out, it was not
properly transmitted, and that is the unfortunate thing.” In addition
to the earthwork, the money budgeted would also fund the building of
quarters for essential staff at the airport, according to the state
government. Before Uduaghan became the Governor of Delta state, his
predecessor had built an airstrip at Asaba, but seeing the economic
potential of having a full airport in the capital, Uduaghan’s
administration embarked on building an airport for big body aircraft,
looking at the business communities all around Asaba. “The desire to go
beyond just having an airstrip as thought by the last administration to
me makes an economic sense, because the Asaba airport will be fed by
passenger traffic from the Onitsha, Nnewi axis and other key areas of
the South East. We also considered the cargo activity at the airport;
that is why we embarked on the airport project,” the Governor explained.
But the snag was that the there was no stretch of level land for about
four kilometers that could take the airport, so the government had to do
with what was available. “We wanted to build an airport with a runway
length of between 3.4 kilometre and four kilometers, unfortunately,
there is no terrain in Asaba area that could give us such stretch of
land; the topography here in Asaba is mainly either hills, or low lands,
rivers almost like a valley. With all the directions and technical
survey that was done for the airport, we got where we are now, which
gives us two terrains, the hill on one side and the river on the other
side, we have to make do with what is available.” He said that his
administration had to embark on the project with serious and heavy
engineering work, dealing with all challenges offered by the topography,
including this latest one, which is leveling the whole surrounding of
the runway and cutting the hill at its end. Meanwhile, the airport is
already providing service for the teeming businessmen and women in
Onitsha and its environs as airlines operating into the airport enjoy
full load factor on every flight.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment